Skip to main content
Blog
← Back to Blog

Can I Sue a Texas University for Breach of Contract?

The University of Texas Tower and Littlefield Fountain on the UT Austin campus

Yes — but not in the courthouse, not on your timeline, and not if you miss a deadline that started running before you knew you had a problem.

A state university signs a contract. Your company performs. The university stops paying, or terminates for cause.

You call your commercial litigator, who tells you what commercial litigators tell you: file suit. File it, and the State will answer with a plea to the jurisdiction — and it will win. Not because your facts are bad. Because the court has no jurisdiction to hear them.

Why a lawsuit against a university fails

Sovereign immunity bars suit against the State unless the Legislature has waived it. A Texas university is the State for this purpose, and the Legislature has not waived immunity for breach of the ordinary contracts a university signs. A suit in district court ends at the plea to the jurisdiction.

Chapter 2260: the process the Legislature provided

What the Legislature provided instead is Chapter 2260 of the Government Code, “Resolution of Certain Contract Claims Against the State” — an administrative process for contract claims that expressly reaches universities. The chapter defines the entities it covers to include “a university system or institution of higher education.” § 2260.001(4).

Chapter 2260 is not a waiver of immunity, § 2260.006, and it does not put you in a courtroom. It is an alternative to litigation, and it has real teeth. Once a contractor files a proper notice of claim, the university is required to negotiate it. § 2260.052(a). If the university does not assert a counterclaim within 60 days, it waives the counterclaim. § 2260.051(d). If negotiation does not resolve the claim, the contractor can force a contested-case hearing before an administrative law judge at the State Office of Administrative Hearings. § 2260.102. The Attorney General defends the university at that hearing and has authority to settle. § 2260.108.

The chapter’s procedures are exclusive, § 2260.005 — this is the forum for the claim. Your contract probably says so; section 2260.004 requires the university to write the dispute-resolution process into every covered contract, and it is usually there, at the end, in the boilerplate.

How a Chapter 2260 claim works

The 180-day deadline

Written notice of the claim must be provided to the university within 180 days of the event giving rise to it. § 2260.051(b). The deadline runs from the event — the termination, the nonpayment, the denied change order — not from the point at which negotiations break down.

That distinction matters because the commercial instinct is to work the problem. Escalate, meet, exchange letters, protect the relationship, keep the next contract alive. Six months of good-faith effort to fix things is six months of a running statutory clock.

The notice must state “with particularity” the nature of the breach, the damages sought, and the legal theory of recovery. § 2260.051(c). A well-drafted notice does more than preserve the claim; it frames the negotiation that the statute then compels.

Timeline: from breach to hearing

  • Day 0. The event giving rise to the claim.
  • By day 180. Written notice of claim delivered to the university. § 2260.051(b).
  • Within 60 days of notice. University must assert any counterclaim or waive it. § 2260.051(d).
  • Within 120 days of the claim. Negotiation must begin. The parties may also agree to mediate. §§ 2260.052(a), .056.
  • Day 270. If the claim is not fully resolved, the contractor may request a contested-case hearing. § 2260.055.
  • Referral. The request is filed with the university, which must refer the claim to SOAH. § 2260.102(c).
  • Hearing. An administrative law judge hears the case and issues written findings. The decision is reviewable only for abuse of discretion. § 2260.104(e).

The $250,000 question

The amount of the claim determines what happens after a hearing.

If the ALJ finds the claim valid and total damages are under $250,000, the university shall pay. § 2260.105(a). That is a mandatory payment obligation, not a judgment to be collected.

If damages are $250,000 or more, the ALJ’s decision takes the form of a report to the Legislature recommending either that it appropriate money to pay the claim or that it not appropriate and deny consent to sue. § 2260.1055. The university must still pay the part of a valid claim that falls below $250,000, § 2260.105(a-1); payment of the balance then depends on an appropriation — a bill through both chambers — and the Legislature meets in regular session every other year. Claims of this size are, for that reason, typically resolved in negotiation or at the hearing stage rather than carried to the Capitol. Settlements are paid from money appropriated to the university for contract claims or for the contract itself, § 2260.054, so where the university’s funds sit is part of the negotiation from the start.

What damages Chapter 2260 allows

Recovery under Chapter 2260 is defined by category. § 2260.003(a). A contractor may recover the unpaid balance of the contract price; the value of additional work the university requested and the contractor actually performed — change orders and extra-work requests, at the agreed price or fair market value; and delay and labor costs the university caused — the added expense of keeping people and equipment on a job because the university, or someone under its control, held things up. Amounts the university is owed for work not performed to the contract are deducted. § 2260.003(b).

Those three categories cover most of what a contractor in a payment or termination dispute is actually seeking. What the chapter does not allow is consequential damages beyond those delay and labor costs, exemplary damages, unjust-enrichment theories, home office overhead, or — outside a narrow construction carve-out under $250,000 — attorney’s fees. § 2260.003(c), (d). Prejudgment interest runs at up to six percent. § 2260.106.

In our experience

When we prepared a notice of claim for a client in 2018, a search of publicly available claims turned up exactly one prior example to work from. There is no standard form, because there is very little practice.

We were hired by a national research firm after a state agency terminated its $675,000 household-travel-survey purchase order “for cause.” The stated ground was our client’s failure to meet a project schedule — a schedule the parties had already agreed to replace. Weeks before the termination, the agency had itself directed our client to stop work on the project, and its own correspondence showed it weighing a termination for convenience instead. We filed the notice of claim under Chapter 2260. When the agency declined to negotiate and refused to make a final offer, we petitioned the executive director for a contested-case hearing and served a petition with the full documentary record attached. The matter settled before hearing.

We were hired by a steel fabricator on a large university construction project to give a second opinion on a claim of roughly $14 million. Another firm had already analyzed the claim and drafted a Chapter 2260 notice. We reached a different conclusion.

This was a construction contract with an amount in controversy far above $250,000 — and that combination is precisely what takes a claim out of Chapter 2260. Since 2013, a breach claim on a written contract for construction services, or materials related to them, at or above $250,000 belongs in district court under Chapter 114 of the Civil Practice and Remedies Code, and section 114.012 makes that remedy exclusive.

The bottom line

A Texas university cannot be sued for breach of an ordinary contract, but it can be made to answer for one. Chapter 2260 gives a contractor what a lawsuit cannot: a claim the university is required to negotiate, a hearing it cannot refuse, and, below $250,000, a payment obligation it cannot avoid. What the process asks in return is precision at the start — a notice filed inside the 180-day window, a clear answer to whether Chapter 2260 or Chapter 114 governs the contract, and a notice of claim written as the pleading it is, stating the breach, the damages, and the legal theory with enough particularity to frame everything that follows. Those decisions are made in the first weeks after a breach, and they determine whether the claim is heard at all.

Bill Cobb is a founding partner of Cobb & Gervasi PLLC and the former Deputy Attorney General for Civil Litigation at the Texas Office of the Attorney General.


Past results afford no guarantee of future outcomes; every case is different and must be evaluated separately on its merits. Attorney Advertising. For informational purposes only. No attorney-client relationship is formed by use of this website.